Resource Allocation and Leveling in Construction Management Projects with Resource Histogram

Received: 10 December 2020    Accepted: 17 December 2020    Published: 31 December 2020
Views:       Downloads:
Abstract

Resource allocation and leveling in construction management projects have been an enthusiastic subject to plenty of researchers since the advancement of the scheduling techniques. Many researchers have studied various versions of the benchmark resource leveling and allocation optimization problems using various scheduling techniques. However, in this study, a straightforward scheduling technique called resource histogram is utilized to allocate and level the available resources. Moreover, the maximum number of resources at peak time is considered as a significant aspect of the case study. Since peak demand isn’t a preferred by the contractor. The effects of resources are also examined in order to demonstrate the variation of the total duration of the project which provides flexibility to decision-makers in making intelligent decisions regarding the use of the resources. Thereby, a construction project with seven activities taken from the technical literature is examined with constrained as well as unconstrained conditions using Microsoft Excel. However, task scheduling is performed using critical path method (CPM). The results indicate that limitation on resources significantly affect the performance and cause the project to be extended beyond the scheduled duration. Moreover, besides renewable, non-renewable resources (e.g., cost demand) may also be significant parameters and this extension can be considered in future research.

Published in American Journal of Engineering and Technology Management (Volume 5, Issue 6)
DOI 10.11648/j.ajetm.20200506.11
Page(s) 91-95
Creative Commons

This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited.

Copyright

Copyright © The Author(s), 2024. Published by Science Publishing Group

Keywords

Resource Leveling, Optimization, Resource Histogram, Peak Time, Resource Allocation

References
[1] Eirgash, M. A., Toğan, V., and Dede, T. (2019). “A multi-objective decision-making model based on TLBO for the time–cost trade-off problems.” Struct. Eng. Mech., 71 (2), 139-151.
[2] Toğan, V., and Eirgash, M. A. (2019a). “Time-cost trade-off optimization of construction projects using teaching learning-based optimization.” KSCE J. Civ. Eng., 23 (1), 10–20.
[3] Chen P, Weng H. "A two-phase GA model for resource-constrained project scheduling," AUTOMAT CONSTR, 32 (1), 9-17, 2009.
[4] Wuliang P, Chengen W. "A multi-mode resource-constrained discrete time–cost tradeoff problem and its genetic algorithm based solution," International Journal of Project Management, 201 (2), 09-18, 2009.
[5] Eirgash, M. A., Toğan, V., and Dede, T. Başağa. H. B. “Time-Cost Trade off Optimization for Construction Projects Using an Optimization Engine.” Eurasian Journal of Engineering Sciences and Technology, 1 (2017) 54-68.
[6] Castro Lacouture D, Suer GA, Gonzalez Joaqui J, Yates JK. "Construction project scheduling with time, cost, and material restrictions using fuzzy mathematical models and critical path method," J CONSTR ENG M, 135 (10), 1096-104, 2009.
[7] M. E. Georgy, “Evolutionary resource scheduler for linear projects,” Automation in Construction, vol. 17, no. 5, pp. 573–583, 2008.
[8] M. H. Elwany, I. E. Korish, M. A. Barakat, and S. M. Hafez, “Resource smoothening in repetitive projects,” Computers and Industrial Engineering, vol. 35, no. 3-4, pp. 415–418, 1998.
[9] Rao, Singiresu S. 1976. Journal of the Operational Research Society Engineering Optimization.
[10] Hegazy, Tarek. “Optimization of Resource Allocation and Leveling Using Genetic Algorithms.” Journal of construction engineering and management 1999; 125 (3): 167–75.
[11] Iranagh, Mahdi Abbasi, and Rifat Sonmez. “A Genetic Algorithm for Resource Leveling.” 2012; 1047–54.
[12] G. Lucko, “Integrating efficient resource optimization and linear schedule analysis with singularity functions,” Journal of Construction Engineering and Management, vol. 137, no. 1, pp. 45–55, 2011.
[13] Garmsiri M, Abassi MR (2012). Resource leveling scheduling by an ant colony-based model. Journal of Industrial Engineering International 8: 1–9.
[14] Khanzadi M, Kaveh A, Alipour M, Aghmiuni HK (2016). Application of CBO and CSS for resource allocation and resource leveling problem. Iranian Journal of Science and Technology, Transactions of Civil Engineering 40: 1–10.
[15] Cheng MY, Tran DH (2015). Opposition-based multiple objective differential evolution (OMODE) for optimizing work shift schedules. Automation in Construction 55: 1–14.
Cite This Article
  • APA Style

    Mohammad Azim Eirgash. (2020). Resource Allocation and Leveling in Construction Management Projects with Resource Histogram. American Journal of Engineering and Technology Management, 5(6), 91-95. https://doi.org/10.11648/j.ajetm.20200506.11

    Copy | Download

    ACS Style

    Mohammad Azim Eirgash. Resource Allocation and Leveling in Construction Management Projects with Resource Histogram. Am. J. Eng. Technol. Manag. 2020, 5(6), 91-95. doi: 10.11648/j.ajetm.20200506.11

    Copy | Download

    AMA Style

    Mohammad Azim Eirgash. Resource Allocation and Leveling in Construction Management Projects with Resource Histogram. Am J Eng Technol Manag. 2020;5(6):91-95. doi: 10.11648/j.ajetm.20200506.11

    Copy | Download

  • @article{10.11648/j.ajetm.20200506.11,
      author = {Mohammad Azim Eirgash},
      title = {Resource Allocation and Leveling in Construction Management Projects with Resource Histogram},
      journal = {American Journal of Engineering and Technology Management},
      volume = {5},
      number = {6},
      pages = {91-95},
      doi = {10.11648/j.ajetm.20200506.11},
      url = {https://doi.org/10.11648/j.ajetm.20200506.11},
      eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.ajetm.20200506.11},
      abstract = {Resource allocation and leveling in construction management projects have been an enthusiastic subject to plenty of researchers since the advancement of the scheduling techniques. Many researchers have studied various versions of the benchmark resource leveling and allocation optimization problems using various scheduling techniques. However, in this study, a straightforward scheduling technique called resource histogram is utilized to allocate and level the available resources. Moreover, the maximum number of resources at peak time is considered as a significant aspect of the case study. Since peak demand isn’t a preferred by the contractor. The effects of resources are also examined in order to demonstrate the variation of the total duration of the project which provides flexibility to decision-makers in making intelligent decisions regarding the use of the resources. Thereby, a construction project with seven activities taken from the technical literature is examined with constrained as well as unconstrained conditions using Microsoft Excel. However, task scheduling is performed using critical path method (CPM). The results indicate that limitation on resources significantly affect the performance and cause the project to be extended beyond the scheduled duration. Moreover, besides renewable, non-renewable resources (e.g., cost demand) may also be significant parameters and this extension can be considered in future research.},
     year = {2020}
    }
    

    Copy | Download

  • TY  - JOUR
    T1  - Resource Allocation and Leveling in Construction Management Projects with Resource Histogram
    AU  - Mohammad Azim Eirgash
    Y1  - 2020/12/31
    PY  - 2020
    N1  - https://doi.org/10.11648/j.ajetm.20200506.11
    DO  - 10.11648/j.ajetm.20200506.11
    T2  - American Journal of Engineering and Technology Management
    JF  - American Journal of Engineering and Technology Management
    JO  - American Journal of Engineering and Technology Management
    SP  - 91
    EP  - 95
    PB  - Science Publishing Group
    SN  - 2575-1441
    UR  - https://doi.org/10.11648/j.ajetm.20200506.11
    AB  - Resource allocation and leveling in construction management projects have been an enthusiastic subject to plenty of researchers since the advancement of the scheduling techniques. Many researchers have studied various versions of the benchmark resource leveling and allocation optimization problems using various scheduling techniques. However, in this study, a straightforward scheduling technique called resource histogram is utilized to allocate and level the available resources. Moreover, the maximum number of resources at peak time is considered as a significant aspect of the case study. Since peak demand isn’t a preferred by the contractor. The effects of resources are also examined in order to demonstrate the variation of the total duration of the project which provides flexibility to decision-makers in making intelligent decisions regarding the use of the resources. Thereby, a construction project with seven activities taken from the technical literature is examined with constrained as well as unconstrained conditions using Microsoft Excel. However, task scheduling is performed using critical path method (CPM). The results indicate that limitation on resources significantly affect the performance and cause the project to be extended beyond the scheduled duration. Moreover, besides renewable, non-renewable resources (e.g., cost demand) may also be significant parameters and this extension can be considered in future research.
    VL  - 5
    IS  - 6
    ER  - 

    Copy | Download

Author Information
  • Department of Civil Engineering, Karadeniz Technical University, Trabzon, Turkey

  • Sections