Study on the Application of BIM5D in Modular Prefabricated Building Project in Changsha Makeshift Hospital

Received: 15 December 2022    Accepted: 1 February 2023    Published: 10 February 2023
Views:       Downloads:
Abstract

Building makeshift hospitals is one of the important measures to deal with the COVID-19 outbreak, which has brought great pressure and challenges to China's public health system. Makeshift hospital construction usually uses prefabricated boxes, which provide faster construction, safer manufacturing, better quality control and lower environmental pollution compared with traditional on-site construction. In the process of procurement, transportation and installation of prefabricated boxes, there will usually be installation deviation, material failure to arrive in time leading to labor slowdown, low efficiency of hoisting and installation, poor coordination among different professions and other problems. Taking Changsha makeshift hospital project as an example, this paper analyzes the application of BIM5D technology in the processing of prefabricated components, the layout of construction site, construction simulation, construction cost management and construction schedule management, and concludes that the use of BIM5D technology in the construction management stage of the prefabricated construction project of makeshift hospital can greatly improve the management and control ability of the management personnel. Obviously improve the quality of prefabricated buildings, save time and cost, through the BIM5D information integration and construction simulation to make the construction management of prefabricated buildings more efficient coordination.

Published in Science Discovery (Volume 11, Issue 1)
DOI 10.11648/j.sd.20231101.11
Page(s) 1-6
Creative Commons

This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited.

Copyright

Copyright © The Author(s), 2024. Published by Science Publishing Group

Keywords

BIM Technology, Modularization, Mobile Cabin Hospital, Prefabricated

References
[1] 周小儒, 马阳, 李莹, 周凹凸. 疫情下的方舱医院设计 [J]. 创意与设计, 2021 (02): 33-39.
[2] 任小玲, 周逸铖, 陈伟刚, 周观根. 基于BIM5D技术的医院工程造价全过程精细化管理 [J]. 建筑经济, 2022, 43 (S1): 204-208.
[3] 田林倩, 姜仁贵, 朱记伟, 张国红, 卫星凯, 刘新怡. 基于BIM5D的建筑工程施工阶段动态管理及优化研究 [J]. 建筑经济, 2022, 43 (S1): 487-491.
[4] 殷保国, 马耕, 江乾. BIM5D技术在超大型施工项目管理中的应用 [J]. 建筑经济, 2021, 42 (12): 73-79.
[5] 刘德富, 彭兴鹏, 刘绍军, 周小冬, 张先龙, 陈国清. BIM~ (5D) 在工程项目管理中的应用 [J]. 施工技术, 2017, 46 (S2): 720-723.
[6] 姚正勇, 张智鹏, 焦丽丽. BIM技术在方舱医院建设中的应用 [J]. 房地产世界, 2022 (21): 151-153.
[7] 邬艳婷, 谢杰, 张海威. 方舱医院快速化建造设计实践 [J]. 中外建筑, 2022 (07): 26-29+19. 2022. 07. 004.
[8] 刘富海. BIM技术在昆明官渡医院工程建设中的应用研究 [J]. 铁道建筑技术, 2021 (11): 170-174.
[9] 李新伟, 曾启, 樊则森. 基于BIM技术的设计与施工协同工作模式研究 [J]. 施工技术, 2020, 49 (05): 68-71+90.
[10] 蔡志立,张季超,陈兆荣. EPC管理视角下预制装配整体式设计与施工一体化探索 [J]. Science Discovery, 2022; 10 (4): 270-278.
[11] 陈兆荣,张季超,蔡志立. 基于模块化装配整体式的精益建造及工程实践 [J]. Science Discovery, 2022; 10 (5): 230-238.
[12] 张海东, 徐宁, 方坤. 某装配式住宅项目结构设计和BIM应用 [J]. 建筑结构, 2019, 49 (11): 62-66. 2019. 11. 012.
[13] 王晶, 夏新. 智慧医疗下的方舱医院信息化建设 [J]. 中国数字医学, 2020, 15 (06): 19-20+24.
[14] C. Merschbrock, B. E. Munkvold, Effffective digital collaboration in the construction industry–a case study of BIM deployment in a hospital construction project, Comput. Ind. 73 (2015) 1–7,. 2015. 07. 003.
[15] R. Manning, J. Messner, Case studies in BIM implementation for programming of healthcare facilities, J. Inf. Technol. Constr. 13 (2008) 446–457.
[16] T. Tan, K. Chen, F. Xue, W. Lu, Barriers to Building Information Modeling (BIM) implementation in China’s prefabricated construction: an interpretive structural modeling (ISM) approach, J. Clean. Prod. 219 (2019) 949–959. 2019. 02. 141
[17] 陈戊荣, 陈兆荣, 苏运升, 李雯琪, 尹烨, 温丽娟, 李若羽, 陈唯军. 气膜性建筑结构核酸检测实验室的创新设计研究 [J]. 建筑结构, 2022, 52 (S1): 698-703.
[18] 李正焜, 叶飞, 李尚. 基于BIM5D技术的工程项目全过程管理研究 [J]. 浙江水利水电学院学报, 2020, 32 (06): 53-58.
[19] 王雨薇, 朱记伟, 杨党锋, 袁荣丽. 基于BIM5D的建筑工程施工动态管理及资源优化 [J]. 施工技术, 2019, 48 (S1): 249-253.
Cite This Article
  • APA Style

    Zhang Guosheng, Cai Zhili, Chen Zhaorong, Liao Fei, Chen Wurong, et al. (2023). Study on the Application of BIM5D in Modular Prefabricated Building Project in Changsha Makeshift Hospital. Science Discovery, 11(1), 1-6. https://doi.org/10.11648/j.sd.20231101.11

    Copy | Download

    ACS Style

    Zhang Guosheng; Cai Zhili; Chen Zhaorong; Liao Fei; Chen Wurong, et al. Study on the Application of BIM5D in Modular Prefabricated Building Project in Changsha Makeshift Hospital. Sci. Discov. 2023, 11(1), 1-6. doi: 10.11648/j.sd.20231101.11

    Copy | Download

    AMA Style

    Zhang Guosheng, Cai Zhili, Chen Zhaorong, Liao Fei, Chen Wurong, et al. Study on the Application of BIM5D in Modular Prefabricated Building Project in Changsha Makeshift Hospital. Sci Discov. 2023;11(1):1-6. doi: 10.11648/j.sd.20231101.11

    Copy | Download

  • @article{10.11648/j.sd.20231101.11,
      author = {Zhang Guosheng and Cai Zhili and Chen Zhaorong and Liao Fei and Chen Wurong and Su Yunsheng and Wu Jiafu},
      title = {Study on the Application of BIM5D in Modular Prefabricated Building Project in Changsha Makeshift Hospital},
      journal = {Science Discovery},
      volume = {11},
      number = {1},
      pages = {1-6},
      doi = {10.11648/j.sd.20231101.11},
      url = {https://doi.org/10.11648/j.sd.20231101.11},
      eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.sd.20231101.11},
      abstract = {Building makeshift hospitals is one of the important measures to deal with the COVID-19 outbreak, which has brought great pressure and challenges to China's public health system. Makeshift hospital construction usually uses prefabricated boxes, which provide faster construction, safer manufacturing, better quality control and lower environmental pollution compared with traditional on-site construction. In the process of procurement, transportation and installation of prefabricated boxes, there will usually be installation deviation, material failure to arrive in time leading to labor slowdown, low efficiency of hoisting and installation, poor coordination among different professions and other problems. Taking Changsha makeshift hospital project as an example, this paper analyzes the application of BIM5D technology in the processing of prefabricated components, the layout of construction site, construction simulation, construction cost management and construction schedule management, and concludes that the use of BIM5D technology in the construction management stage of the prefabricated construction project of makeshift hospital can greatly improve the management and control ability of the management personnel. Obviously improve the quality of prefabricated buildings, save time and cost, through the BIM5D information integration and construction simulation to make the construction management of prefabricated buildings more efficient coordination.},
     year = {2023}
    }
    

    Copy | Download

  • TY  - JOUR
    T1  - Study on the Application of BIM5D in Modular Prefabricated Building Project in Changsha Makeshift Hospital
    AU  - Zhang Guosheng
    AU  - Cai Zhili
    AU  - Chen Zhaorong
    AU  - Liao Fei
    AU  - Chen Wurong
    AU  - Su Yunsheng
    AU  - Wu Jiafu
    Y1  - 2023/02/10
    PY  - 2023
    N1  - https://doi.org/10.11648/j.sd.20231101.11
    DO  - 10.11648/j.sd.20231101.11
    T2  - Science Discovery
    JF  - Science Discovery
    JO  - Science Discovery
    SP  - 1
    EP  - 6
    PB  - Science Publishing Group
    SN  - 2331-0650
    UR  - https://doi.org/10.11648/j.sd.20231101.11
    AB  - Building makeshift hospitals is one of the important measures to deal with the COVID-19 outbreak, which has brought great pressure and challenges to China's public health system. Makeshift hospital construction usually uses prefabricated boxes, which provide faster construction, safer manufacturing, better quality control and lower environmental pollution compared with traditional on-site construction. In the process of procurement, transportation and installation of prefabricated boxes, there will usually be installation deviation, material failure to arrive in time leading to labor slowdown, low efficiency of hoisting and installation, poor coordination among different professions and other problems. Taking Changsha makeshift hospital project as an example, this paper analyzes the application of BIM5D technology in the processing of prefabricated components, the layout of construction site, construction simulation, construction cost management and construction schedule management, and concludes that the use of BIM5D technology in the construction management stage of the prefabricated construction project of makeshift hospital can greatly improve the management and control ability of the management personnel. Obviously improve the quality of prefabricated buildings, save time and cost, through the BIM5D information integration and construction simulation to make the construction management of prefabricated buildings more efficient coordination.
    VL  - 11
    IS  - 1
    ER  - 

    Copy | Download

Author Information
  • China Construction Fifth Engineering Bureau the Third Construction Co., Ltd., Changsha, China

  • China Construction Fifth Engineering Bureau the Third Construction Co., Ltd., Changsha, China

  • China Construction Fifth Engineering Bureau the Third Construction Co., Ltd., Changsha, China

  • China Construction Fifth Engineering Bureau the Third Construction Co., Ltd., Changsha, China

  • BGI Genomics Co., Ltd, Shenzhen, China

  • College of Design and Innovation, Tongji University, Shanghai, China

  • China Construction Fifth Engineering Bureau the Third Construction Co., Ltd., Changsha, China

  • Sections