Contribution of Risk Factors for Infrastructure Development of Nepal

Received: 12 January 2017    Accepted: 25 January 2017    Published: 14 March 2017
Views:       Downloads:
Abstract

All most all infrastructure projects are being over running in terms of either time or amount and even deteriorated the quality of the projects. For new professionals and the experts are learning bad train which must be stop it as soon as possible. This is because of contributed risk factors, No body, either government agency of Nepal take care about this risk factors or from public, the infrastructure projects which are losing a lot every minute, quality and money. This research explores to analyze, and mitigate the understanding of risk management in the infrastructures development projects. Deeper understanding by means of detailed study during pre-planning and planning phase is expected to enhance more effective risk management and, therefore, a better productivity and better quality to be achieved, which creates the satisfactions to all stakeholders.

Published in American Journal of Civil Engineering (Volume 5, Issue 3)
DOI 10.11648/j.ajce.20170503.11
Page(s) 124-131
Creative Commons

This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited.

Copyright

Copyright © The Author(s), 2024. Published by Science Publishing Group

Keywords

Risk Factors, Infrastructures, Development, GDP, Household

References
[1] Al-Bahar, J. (1988).'Risk Management Approach for Construction Projects: a systmatic analytical approach for contractor, Ph. D. thesis', University of California, Berkeley, CA.
[2] Annual Household Survey, 2012/13, (2014). Government of Nepal, National Planning Commission secretariat, Central Bureau of statistics, may 2014, Published by Central Bureau of Statistics, Thapathali, Kathmandu, Nepal.
[3] Economy survey. (2010) Minister of Finance, Singadarbar Kathmandu, Nepal.
[4] Hemmati, A. Hemmati, M. and Mohammad (2012). 'The Acquaintance with Organizational Maturity Model of Project Management', Middle-East Journal of Scientific Research 12 (10): 1391-1395, ISSN 1990-9233, IDOSI Publications, DOI: 10.5829/idosi.mejsr.2012.12.10.67, Abhar Branch, Islamic Azad University, Abhar, Iran. 1391.
[5] Kerzner, H. (2001). "Project Management" CBS Publishers & Distributers, India.
[6] Koirala, M. P. (2014), Risk in housing and real estate Construction Project, Journal of the Institute of Engineering vol-10, No. 1, pp 34-44. TUTA/IOE/PCU.
[7] Koirala, M. P. (2012). Urban Development Projects and risk management in Nepal, Journal of Research & Innovation (JORI), vol. 1, November 2012, Post Graduate Student society.
[8] Koirala, M. P., (2012). Risk in Housing and Real Estate Construction Project Study in Nepal. A thesis submitted to the Singhania university, Rajasthan, India, in partial fulfillment of the requirement for the degree of Doctor of Philosophy in Engineering.
[9] Leung, M. y. Chan, Y. S. and Yu, J. (2009). 'Integrated Model for the Stressors and Stresses of Construction Project Managers in Hong Kong', Journal of Construction Engineering and Management, Vol. 135, No. 2, February 1, 2009, ISSN 0733- 9364/2009/2- 126134. DOI: 10.1061/(ASCE)0733- 9364(2009)135: 2 (126).
[10] Morris, P. W. G., Crawford, L. D., Hodgson, Shepherd, M. M. Thomas, J. (2006).'Exploring the role of formal bodies of knowledge in defininga profession – The case of project management', International Journal of Project Management 24 (2006) 710–721, Published by Elsevier Ltd and IPMA., doi: 10.1016/j.ijproman.2006.09.012.
[11] Nepal: Addressing the Employment Challenge, through the Sectoral Pattern of Growth report prepared for the International Labour Organization, ILO Country office for Nepal April 2014, ILO Publications, International Labour Office, CH-1211 Geneva 22, Switzerland., Printed in Nepal.
[12] Oberlender, G. D. (1993).'Project Management For Engineering And Management' McGraw-Hill Inc, New York.
[13] Shrestha, R. S. (2011). The Kantipur Daily, 2 march, Kantipur Publication.
[14] Water Resources of Nepal In The Context of Climate Change. (2011). Water and Energy Commission Secretariat. Singha Durbar, Kathmandu, NepalWebsite: www.wec.gov.np.
[15] Yang, J. B. Peng S. C. (2008). 'Development of a customer satisfaction evaluation model forconstruction project management', Building and Environment 43 458–468, Institute of Construction Management, Chung Hua University, No. 707, Sec. 2, Wu-Fu Rd., Hsinchu 300, Taiwan.
Cite This Article
  • APA Style

    Madhav Prasad Koirala. (2017). Contribution of Risk Factors for Infrastructure Development of Nepal. American Journal of Civil Engineering, 5(3), 124-131. https://doi.org/10.11648/j.ajce.20170503.11

    Copy | Download

    ACS Style

    Madhav Prasad Koirala. Contribution of Risk Factors for Infrastructure Development of Nepal. Am. J. Civ. Eng. 2017, 5(3), 124-131. doi: 10.11648/j.ajce.20170503.11

    Copy | Download

    AMA Style

    Madhav Prasad Koirala. Contribution of Risk Factors for Infrastructure Development of Nepal. Am J Civ Eng. 2017;5(3):124-131. doi: 10.11648/j.ajce.20170503.11

    Copy | Download

  • @article{10.11648/j.ajce.20170503.11,
      author = {Madhav Prasad Koirala},
      title = {Contribution of Risk Factors for Infrastructure Development of Nepal},
      journal = {American Journal of Civil Engineering},
      volume = {5},
      number = {3},
      pages = {124-131},
      doi = {10.11648/j.ajce.20170503.11},
      url = {https://doi.org/10.11648/j.ajce.20170503.11},
      eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.ajce.20170503.11},
      abstract = {All most all infrastructure projects are being over running in terms of either time or amount and even deteriorated the quality of the projects. For new professionals and the experts are learning bad train which must be stop it as soon as possible. This is because of contributed risk factors, No body, either government agency of Nepal take care about this risk factors or from public, the infrastructure projects which are losing a lot every minute, quality and money. This research explores to analyze, and mitigate the understanding of risk management in the infrastructures development projects. Deeper understanding by means of detailed study during pre-planning and planning phase is expected to enhance more effective risk management and, therefore, a better productivity and better quality to be achieved, which creates the satisfactions to all stakeholders.},
     year = {2017}
    }
    

    Copy | Download

  • TY  - JOUR
    T1  - Contribution of Risk Factors for Infrastructure Development of Nepal
    AU  - Madhav Prasad Koirala
    Y1  - 2017/03/14
    PY  - 2017
    N1  - https://doi.org/10.11648/j.ajce.20170503.11
    DO  - 10.11648/j.ajce.20170503.11
    T2  - American Journal of Civil Engineering
    JF  - American Journal of Civil Engineering
    JO  - American Journal of Civil Engineering
    SP  - 124
    EP  - 131
    PB  - Science Publishing Group
    SN  - 2330-8737
    UR  - https://doi.org/10.11648/j.ajce.20170503.11
    AB  - All most all infrastructure projects are being over running in terms of either time or amount and even deteriorated the quality of the projects. For new professionals and the experts are learning bad train which must be stop it as soon as possible. This is because of contributed risk factors, No body, either government agency of Nepal take care about this risk factors or from public, the infrastructure projects which are losing a lot every minute, quality and money. This research explores to analyze, and mitigate the understanding of risk management in the infrastructures development projects. Deeper understanding by means of detailed study during pre-planning and planning phase is expected to enhance more effective risk management and, therefore, a better productivity and better quality to be achieved, which creates the satisfactions to all stakeholders.
    VL  - 5
    IS  - 3
    ER  - 

    Copy | Download

Author Information
  • Department of Civil and Architect, Member of Subject Committee, Pokhara University, Pokhara, Nepal

  • Sections