| Peer-Reviewed

Investigating Causes of Construction Delay in Ethiopian Construction Industries

Received: 17 October 2016    Accepted: 4 November 2016    Published: 2 December 2016
Views:       Downloads:
Abstract

Construction delays are occurring in every phase of a construction project and are common problems in construction projects in Ethiopia. Moreover, it is well known that the delays in construction projects are the major causes of project failure. If the delay is not identified and the corrective project management decision is not taken in time a project may incur extra cost and extension of project time, which gives rise to dissatisfaction to all the parties involved and nowadays it’s becoming a major obstruction for their development for developing countries like Ethiopia. This research first identified 88 key factors causing delay in Ethiopian construction industries, and then the most common and critical causes of construction delay were evaluated by using both the data collected in a survey of construction managers, resident engineers, contractors, and clients, and interviews with senior professionals in the field. The findings show that the main critical factors that cause construction delays in Ethiopia are: (1) Difficulties in financing project by a contractor; (2) Escalation of the materials price; (3) Infective project planning; (4) Scheduling or resource management; (5) Delay in progress payments for completed works, (6) Lack of skilled professionals in the field of construction management in the organization, and (7) Fluctuating labor availability season to season /Seasonal labors availability. This study shows that in Ethiopia only 8.25% projects have been finished to the original targeted completion date. The remaining 91.75% delayed 352% of its contractual time. This paper finally came up with solutions towards reducing the impact of delays on construction projects in Ethiopia.

Published in Journal of Civil, Construction and Environmental Engineering (Volume 1, Issue 1)
DOI 10.11648/j.jccee.20160101.13
Page(s) 18-29
Creative Commons

This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited.

Copyright

Copyright © The Author(s), 2024. Published by Science Publishing Group

Keywords

Construction Delay, Delay Causes, Top-Ten Delay Factors

References
[1] Iyer, K. C., Jha, K. N., 2005. Factors affecting cost performance: evidence from Indian construction projects. International Journal of Project Management 23, 283–295.
[2] Assaf, S. A. and S. Al-Hejji, 2006. Causes of delay in large construction projects”, international journal of project managements, 24: 349-357.
[3] Takim, R., & Akintoye, A. (2002). A conceptual model for successful construction project performance. Paper presented at 2nd International Postgraduate Research Conference in Built and Human Environment.
[4] Ministry of Works and Urban Development (MoWUD), (2006), Plan for Accelerated and Sustained Development to End Poverty (PASDEP), (2005/06-2009/10); Urban Development & Construction Industry component of PASDEP.
[5] Wubishet, J. M., (2004) Performances for Public Construction Projects in (Least) Developing Countries, Federal Road and Educational Building Projects in Ethiopia, Doctoral Thesis, NTNU, Trondheim.
[6] Abdalla, M. Odeh and Hussien T. Battaineh, (2000), Causes of construction delay: Traditional Contracts, International Journal of Project Management 20(2002) 67–73.
[7] Mansfield, N. R. Causes of delay and cost overruns in Nigerian construction projects. Int J Project Manage 1994; 12(4):254–60.
[8] Sambasivan M, W. S. (2007). Causes and effects of delays in Malaysian construction industries. International Journal of Project Management, 25 (5), 517-526.
[9] Al-Momani, A. H. (2000). Construction delay: a quantitative analysis, Journal of Project Management 18, 51-59.
[10] Chan DWW, K. M. (1996). Reasons for delay in civil Engineering projects in case of Hong Kong. Hong Kong Instit Eng Trans, 3, 1-8.
[11] Mezher, T. M. and Tawil, W. (1998) Causes of delays in the construction industry in Lebanon. Engineering, Construction and Architectural Management 5(3), 252-260.
[12] Frimpong, Y., Oluwoye, J. and Crawford, L. (2003). Causes of delay and cost overruns in construction of groundwater projects in developing countries: Ghana as a case study. International Journal of Project Management 21: pp. 321-26.
[13] Mansfield, N. R., Ugwu, O. O. and Doran, T. (1994) Causes of delay and cost overruns in Nigerian construction projects. International Journal of Project Management 12(4):pp. 254–60.
[14] Fugar, F. D., & Agyakwah-Baah, A. B. (2010). Delays in building construction projects in Ghana. Australasian Journal of Construction Economics and Building, 10(1/2), 103-116.
[15] Hamzah, N., Khoiry, M. A., Arshada I., Tawil, N. M., & Che Ani, A. I. (2011). Cause of Construction Delay - Theoretical Framework. 2nd International Building Control Conference 2011, Procedia Engineering, 20, 490 – 495.
[16] Kikawasi, G. (2012). Causes and effects of delays and disruptions in construction project in Tanzania. Australasian Journal on Construction Economics and Building, Conference Series, 1(2), 52-59.
[17] Mahamid, I. (2013). Common risks affecting time overrun in road construction projects in Palestine: Contractor's' perspective. Australasian Journal of Construction Economics and Building, 13(2): 45-52.
[18] Mohammed, K. A. (2012). Causes of Delay in Nigerian Construction Industry. Interdisciplinary Journal of Contemporary Research in Business, 4, 785-794.
[19] Fung I. W. H., L. T. (2006). Construction Delays in Hong Kong civil engineering projects. Journal of construction engineering management, 132 (6), 639-49.
[20] O. E. Akinsiku and A. Akinsulire (2012). Stakeholders’ Perception of the Causes and Effects of Construction Delays on Project Delivery. KICEM Journal of Construction Engineering and Project Management. 2(4) 25-31.
[21] N. Hamzah, M. A. Khoiry, I. Arshad, W. H. W. Badaruzzaman, and N. M. Tawil (2012). Identification of the Causes of Construction Delay in Malaysia. International Journal of Civil, Architectural, Structural and Construction Engineering 6 (12), 105-110.
[22] Abedi, M., Fathi, M. S., & Mohammad, M. F. (2011). Major Causes of Construction Delays under Client Category and Contractor Category. The First Iranian Students Scientific Conference in Malaysia, 9 & 10 Apr 2011, UPM, Malaysia.
[23] Mohamed M. Marzouk, Tarek I. El-Rasas (2014). Analyzing delay causes in Egyptian construction projects. Journal of Advanced Research, 5, 49–55.
[24] Ogunlana, SO, Olomolaiye, PO (1989). A survey of site management practice on some selected sites in Nigeria. Building Environ 24 (2), 191-6.
[25] Syed M. Ahmed, S. A., Pragnya Kappagantula, and Dharam Gollapudi (2003). Delays in Construction: A Brief Study of the Florida Construction Industry. ASC Proceedings of the 39th Annual Conference Clemson University Clemson, South Carolina.
[26] Kang sik wei (2010). Causes, effects and methods of minimizing Delays in construction projects. Journal Of Management In Engineering, 312-332.
[27] Le-Hoai, L., Lee, Y. D., & Lee, J. D. (2008). Delay and cost overruns in Vietnam large construction projects: a comparison with Other Selected Countries. KSCE Journal of Civil Engineering, 12(6), 367–377.
[28] Pickavance Keith (2005). Delay and disruption in construction contracts. Informa publishing group limited. (3) ISBN-10, 1843114267.
Cite This Article
  • APA Style

    Werku Koshe, K. N. Jha. (2016). Investigating Causes of Construction Delay in Ethiopian Construction Industries. Journal of Civil, Construction and Environmental Engineering, 1(1), 18-29. https://doi.org/10.11648/j.jccee.20160101.13

    Copy | Download

    ACS Style

    Werku Koshe; K. N. Jha. Investigating Causes of Construction Delay in Ethiopian Construction Industries. J. Civ. Constr. Environ. Eng. 2016, 1(1), 18-29. doi: 10.11648/j.jccee.20160101.13

    Copy | Download

    AMA Style

    Werku Koshe, K. N. Jha. Investigating Causes of Construction Delay in Ethiopian Construction Industries. J Civ Constr Environ Eng. 2016;1(1):18-29. doi: 10.11648/j.jccee.20160101.13

    Copy | Download

  • @article{10.11648/j.jccee.20160101.13,
      author = {Werku Koshe and K. N. Jha},
      title = {Investigating Causes of Construction Delay in Ethiopian Construction Industries},
      journal = {Journal of Civil, Construction and Environmental Engineering},
      volume = {1},
      number = {1},
      pages = {18-29},
      doi = {10.11648/j.jccee.20160101.13},
      url = {https://doi.org/10.11648/j.jccee.20160101.13},
      eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.jccee.20160101.13},
      abstract = {Construction delays are occurring in every phase of a construction project and are common problems in construction projects in Ethiopia. Moreover, it is well known that the delays in construction projects are the major causes of project failure. If the delay is not identified and the corrective project management decision is not taken in time a project may incur extra cost and extension of project time, which gives rise to dissatisfaction to all the parties involved and nowadays it’s becoming a major obstruction for their development for developing countries like Ethiopia. This research first identified 88 key factors causing delay in Ethiopian construction industries, and then the most common and critical causes of construction delay were evaluated by using both the data collected in a survey of construction managers, resident engineers, contractors, and clients, and interviews with senior professionals in the field. The findings show that the main critical factors that cause construction delays in Ethiopia are: (1) Difficulties in financing project by a contractor; (2) Escalation of the materials price; (3) Infective project planning; (4) Scheduling or resource management; (5) Delay in progress payments for completed works, (6) Lack of skilled professionals in the field of construction management in the organization, and (7) Fluctuating labor availability season to season /Seasonal labors availability. This study shows that in Ethiopia only 8.25% projects have been finished to the original targeted completion date. The remaining 91.75% delayed 352% of its contractual time. This paper finally came up with solutions towards reducing the impact of delays on construction projects in Ethiopia.},
     year = {2016}
    }
    

    Copy | Download

  • TY  - JOUR
    T1  - Investigating Causes of Construction Delay in Ethiopian Construction Industries
    AU  - Werku Koshe
    AU  - K. N. Jha
    Y1  - 2016/12/02
    PY  - 2016
    N1  - https://doi.org/10.11648/j.jccee.20160101.13
    DO  - 10.11648/j.jccee.20160101.13
    T2  - Journal of Civil, Construction and Environmental Engineering
    JF  - Journal of Civil, Construction and Environmental Engineering
    JO  - Journal of Civil, Construction and Environmental Engineering
    SP  - 18
    EP  - 29
    PB  - Science Publishing Group
    SN  - 2637-3890
    UR  - https://doi.org/10.11648/j.jccee.20160101.13
    AB  - Construction delays are occurring in every phase of a construction project and are common problems in construction projects in Ethiopia. Moreover, it is well known that the delays in construction projects are the major causes of project failure. If the delay is not identified and the corrective project management decision is not taken in time a project may incur extra cost and extension of project time, which gives rise to dissatisfaction to all the parties involved and nowadays it’s becoming a major obstruction for their development for developing countries like Ethiopia. This research first identified 88 key factors causing delay in Ethiopian construction industries, and then the most common and critical causes of construction delay were evaluated by using both the data collected in a survey of construction managers, resident engineers, contractors, and clients, and interviews with senior professionals in the field. The findings show that the main critical factors that cause construction delays in Ethiopia are: (1) Difficulties in financing project by a contractor; (2) Escalation of the materials price; (3) Infective project planning; (4) Scheduling or resource management; (5) Delay in progress payments for completed works, (6) Lack of skilled professionals in the field of construction management in the organization, and (7) Fluctuating labor availability season to season /Seasonal labors availability. This study shows that in Ethiopia only 8.25% projects have been finished to the original targeted completion date. The remaining 91.75% delayed 352% of its contractual time. This paper finally came up with solutions towards reducing the impact of delays on construction projects in Ethiopia.
    VL  - 1
    IS  - 1
    ER  - 

    Copy | Download

Author Information
  • Dept. of Construction Technology & Management, Dire Dawa Institute of Technology, Dire Dawa, Ethiopia

  • Dept. of Civil Engineering, Indian Institute of Technology, Delhi, Hauz Khas, New Delhi, India

  • Sections