| Peer-Reviewed

Estimation of Pre-Compression Parameters in the Acceleration of Consolidation Settlement

Received: 1 April 2014     Accepted: 28 April 2014     Published: 10 May 2014
Views:       Downloads:
Abstract

Pre-compression by preloading is used to accelerate the consolidation settlement of a site ahead of construction so that post-construction settlement would be minimal. The principal aim of the technique is to remove the primary consolidation settlement anticipated under the proposed load with or without partial compensation for secondary compression so that post-construction settlement would consist of a small re-compression and secondary compression. In this paper, the scope of pre-compression is expanded to include partial removal of primary consolidation as a possible settlement management option. Modifications and simplifications are introduced into parameter estimation for design to deal with pre-compressions intended to remove any degree of the primary consolidation and those that go beyond the primary consolidation stage. This provides foundation engineers the flexibility to evaluate different pre-compression load and duration options under different settlement regimes and their implications. A numerical example is used to demonstrate and verify the modifications.

Published in American Journal of Civil Engineering (Volume 2, Issue 3)
DOI 10.11648/j.ajce.20140203.12
Page(s) 68-73
Creative Commons

This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited.

Copyright

Copyright © The Author(s), 2014. Published by Science Publishing Group

Keywords

Pre-Compression, Primary Consolidation, Settlement, Surcharge Load

References
[1] J. A. Knapett, and R. F. Craig, Craig’s Soil Mechanics, 8th ed., Spon Press, New York, 2012.
[2] J. Chu, M. W. Bo, and V. Choa, “Practical considerations for using vertical drains in soil improvement,” Geotextiles and Geomembranes 22, 2004, pp. 101-117.
[3] A. K. Bhattacharya, and S. Basack, “A review of the use of preloading technique and vertical sand drains for soil consolidation,” Proc. Indian Geotechnical Conference, Kochi, December 2011, pp. 15-17.
[4] S. J. Johnson, “Precompression for improving foundation soils,” Journal of Soil Mechanics and Foundation Division, ASCE, vol. 96, No. SM1, 1970, pp. 114-144.
[5] J. D. Brown, and W. G. Paterson, “Failure of an oil storage tank founded on sensitive marine clay,” Canadian Geotechnical Journal, Vol. 1, No. 4, November 1964.
[6] R. D. Darragh, “Controlled water tests to preload tank foundations,” Journal of Soil Mechanics and Foundations Division, ASCE, Vol. 90, No. SM5. September, 1964.
[7] M. Kamiolkowski, R. Lancellotta, and W. Wolski, “Precompression and speeding up consolidation,” General Report, Proc. 8th European Conf. Soil Mech. & Foundation Engrg., Vol. 3, 1983, pp. 1201-1226.
[8] E. C. Loeng, R. A. A. Soemitro, and H. Rhardjo, “Soil improvement by surcharge and vacuum preloading,” Geotechnique, Vol. 50, No. 5, 2000, pp. 601-605.
[9] G. Mesri, M. A. Ajlouni, T. W. Feng, and D. O. K. Lo, “Surcharging of soft ground to reduce secondary settlement,” Proc. 3rd Int. Conf. on Soft Soil Engineering, Hong Kong, December 2001, pp. 55-65.
[10] M. MacVay, and D. Nugyen, “Evaluation of embankment distress at Sander’s Creed-SR20,” Report submitted to the Florida Department of Transportation, UF Contract No. 4910-4504-734, May 2004.
[11] B. M. Das, Principles of Foundation Engineering, 7th ed., Cengage Learning Engineering, 2010.
Cite This Article
  • APA Style

    Yaw Adubofour Tuffour, Mark Adom-Asamoah. (2014). Estimation of Pre-Compression Parameters in the Acceleration of Consolidation Settlement. American Journal of Civil Engineering, 2(3), 68-73. https://doi.org/10.11648/j.ajce.20140203.12

    Copy | Download

    ACS Style

    Yaw Adubofour Tuffour; Mark Adom-Asamoah. Estimation of Pre-Compression Parameters in the Acceleration of Consolidation Settlement. Am. J. Civ. Eng. 2014, 2(3), 68-73. doi: 10.11648/j.ajce.20140203.12

    Copy | Download

    AMA Style

    Yaw Adubofour Tuffour, Mark Adom-Asamoah. Estimation of Pre-Compression Parameters in the Acceleration of Consolidation Settlement. Am J Civ Eng. 2014;2(3):68-73. doi: 10.11648/j.ajce.20140203.12

    Copy | Download

  • @article{10.11648/j.ajce.20140203.12,
      author = {Yaw Adubofour Tuffour and Mark Adom-Asamoah},
      title = {Estimation of Pre-Compression Parameters in the Acceleration of Consolidation Settlement},
      journal = {American Journal of Civil Engineering},
      volume = {2},
      number = {3},
      pages = {68-73},
      doi = {10.11648/j.ajce.20140203.12},
      url = {https://doi.org/10.11648/j.ajce.20140203.12},
      eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.ajce.20140203.12},
      abstract = {Pre-compression by preloading is used to accelerate the consolidation settlement of a site ahead of construction so that post-construction settlement would be minimal. The principal aim of the technique is to remove the primary consolidation settlement anticipated under the proposed load with or without partial compensation for secondary compression so that post-construction settlement would consist of a small re-compression and secondary compression. In this paper, the scope of pre-compression is expanded to include partial removal of primary consolidation as a possible settlement management option. Modifications and simplifications are introduced into parameter estimation for design to deal with pre-compressions intended to remove any degree of the primary consolidation and those that go beyond the primary consolidation stage. This provides foundation engineers the flexibility to evaluate different pre-compression load and duration options under different settlement regimes and their implications. A numerical example is used to demonstrate and verify the modifications.},
     year = {2014}
    }
    

    Copy | Download

  • TY  - JOUR
    T1  - Estimation of Pre-Compression Parameters in the Acceleration of Consolidation Settlement
    AU  - Yaw Adubofour Tuffour
    AU  - Mark Adom-Asamoah
    Y1  - 2014/05/10
    PY  - 2014
    N1  - https://doi.org/10.11648/j.ajce.20140203.12
    DO  - 10.11648/j.ajce.20140203.12
    T2  - American Journal of Civil Engineering
    JF  - American Journal of Civil Engineering
    JO  - American Journal of Civil Engineering
    SP  - 68
    EP  - 73
    PB  - Science Publishing Group
    SN  - 2330-8737
    UR  - https://doi.org/10.11648/j.ajce.20140203.12
    AB  - Pre-compression by preloading is used to accelerate the consolidation settlement of a site ahead of construction so that post-construction settlement would be minimal. The principal aim of the technique is to remove the primary consolidation settlement anticipated under the proposed load with or without partial compensation for secondary compression so that post-construction settlement would consist of a small re-compression and secondary compression. In this paper, the scope of pre-compression is expanded to include partial removal of primary consolidation as a possible settlement management option. Modifications and simplifications are introduced into parameter estimation for design to deal with pre-compressions intended to remove any degree of the primary consolidation and those that go beyond the primary consolidation stage. This provides foundation engineers the flexibility to evaluate different pre-compression load and duration options under different settlement regimes and their implications. A numerical example is used to demonstrate and verify the modifications.
    VL  - 2
    IS  - 3
    ER  - 

    Copy | Download

Author Information
  • Department of Civil Engineering, Kwame Nkrumah University of Science and Technology, Kumasi, Ghana

  • Department of Civil Engineering, Kwame Nkrumah University of Science and Technology, Kumasi, Ghana

  • Sections